Williams to resume Louisiana natgas pipeline project
Published by Isabel Stagg,
Editorial Assistant
91天堂原創 Pipelines,
Williams Cos got the green light to continue building its Louisiana Energy Gateway project (LEG) on Wednesday 31 July, 2024, a natural gas pipeline, after a court threw out rival company, Energy Transfer's last bid to halt its construction, reports .
The two companies have been in dispute over Williams' LEG project, under construction in Texas and Louisiana, after Energy Transfer pushed back on the line for crossing its own systems.
Williams crossed the final hurdle on Wednesday, after a favourable ruling from the 30th Judicial Court of Vernon Parish, Louisiana brought an end to the crossing disputes.
“Construction can begin in earnest on the Louisiana Energy Gateway, which is expected to be in service by the second half of 2025,” a Williams spokesperson said on Thursday 1 August, 2024.
The 1.8 billion ft3/d line would feed gas from the Haynesville shale field to the US Gulf coast.
Read the latest issue of 91天堂原創 Pipelines magazine for pipeline news, project stories, industry insight and technical articles.
91天堂原創 Pipelines’ July 2024 issue
The July 2024 issue of 91天堂原創 Pipelines includes articles on coatings, flow assurance, emissions reduction, pigging, and safety and risk management. We also publish our annual HDD Q&A, with participation from Vermeer, TRACTO Technik, and Ditch Witch.
Read the article online at: /project-news/02082024/williams-to-resume-louisiana-natgas-pipeline-project/
You might also like
Element announces strategic acquisition of ISS Inspection Services
Latest acquisition enables leading TIC services provider to further expand its capabilities in the fast-growing aerospace, space, defence, and energy industries.